Case Study Sample Client
Is wind energy suitable for my business? Below is a sample client, showing the costs and requirements of installing an on-site generator. Every project is different – please enquire about our free site assessment if you’d like to find out more.
A large manufacturing business installs an onsite wind turbine to combat rapidly rising energy prices and growing carbon emission problems. The turbine which provides a large proportion of its energy requirements with no carbon missions and at a competitive price makes both financial and environmental sense saving the company €1.5 Million over 10 years.
The Vital Statistics
- 1500kW 24/7 base load
- Wind Resource: 7m/s mean wind speed at 75m
- Requirement 2MW turbine which will deliver 5GWh per annum
- Significant reduction in client’s energy costs
- Approximately 30% of client’s energy costs are hedged against retail energy price increases for 10 years
- No capital outlay for the client and a full turnkey solution delivered
Typical Project Costs
Feasibility: €7.5k
Planning: €50k
Total Project Costs: €1.8M per MW (approx) Funded by WED
Typical Payback Period: 6-12 years if Owner Operator
(Payback dependent on size of project; % and cost of displaced retail energy and wind resource)
Site Savings
Year 1 Savings: €55,000
Year 5 Cumulative Savings: €442,000
Year 10 Cumulative Savings: €1,500,000